Eversource Transmission Line Structure Replacements

As you may have noticed, several Eversource contractor crews have begun working in Chester to replace aging structures on the 373 and 391 transmission lines. A letter was sent to all affected homeowners, but is attached here as well. 

In summary:

  • SCHEDULE: July 2019 – Winter of 2019
  • SCOPE: Replacing wood structures with weathered steel
  • LOCATIONS:  Pingree Hill Road, Bridle Path Road, and Candia Road
  • CONTRACTORS INCLUDE: Supreme Industries, Blu Roc, PAR, and Michels Power

Eversource thanks you for your patience as they undertake this important maintenance.  If you have further questions, please feel free to reach out to them at (888) 926-5334 or NHProjectsInfo@Eversource.com.   